We successfully completed the project at Al Multaqa and Suhar, for the client M/s. Oman Environmental Services Holding Company (beah) on 24/11/2024. The project consists Supply and Installation of Concrete Slab for the New Leachate Evaporation Ponds at Al Multaqa Landfill and Suhar Landfill.
We have started the school project at Musanah for the client Ministry of Education. The project consists of School Building, Kiosk, Guard Room, Paved Courtyard, Steel Structure Shed, Substation, Electrical works, Interlock Paved Car-parking, Play Court and Compound Wall, amounting to R.O. 1,680,145/-
We successfully completed the Municipality Solid Waste Transfer Station Facility in Quriyat for the client M/s. Oman Environmental Services Holding Company (beah) last month. The project consists of Admin Building, Workshop, Security room, Control room, Pump room, Generator, Internal Asphalt road, Rain Water channel, Kerb-stone, Interlock and Chain-link Fence, Compound wall, amounting to R.O. 1,341,782.600